Demolition of the “Old Gym” was completed on August 18, 2026.
During the Monday night board meeting on August 18, the Board approved Mann Made Construction to begin the bid process for the new gym construction project. We anticipate selecting and approving the bids at the next Board meeting on September 21, 2026.
Our hope is to break ground in early October, with the goal of having the new gym completed and ready for use by August 2027. The worst-case scenario, which we certainly hope to avoid, would be a 12-month construction timeline, putting completion in early October 2027.
As a reminder, this project is for a gym facility only. The building is being designed with future expansion in mind, allowing us to add additional spaces as the need arises and as funding becomes available. At this time, we simply do not have the funds to include additional spaces such as locker rooms, a music room, OAP room, or other similar areas.
While this project is intentionally focused on providing the gym space we need today, the design will allow us to expand the facility in the future as needs and funding allow.
We are excited to see this project moving forward and will continue to provide updates as we reach each major milestone.
If you have any questions, please feel free to reach out.
Thank you,
Jeff Webb